Engineering Management on the FE Industrial and Systems exam

Engineering Management accounts for 9 of the 110 questions — 8.2% of your exam. It sits in the middle of the paper by weight: too big to skip, not big enough to dominate your plan.

Questions9
Share of exam8.2%
Rank by weight7/13
In our bank32

What Engineering Management covers

On the FE Industrial and Systems exam this area covers project management and scheduling, CPM and PERT, organisational structures, leadership and teams, budgeting and cost control, and decision making.

What the questions look like: A critical path or project duration, a float, or a management-principle identification.

Worth knowing cold: Network diagrams are the computational core. The rest is definitional and quick if you know the vocabulary.

3 free Engineering Management practice problems

These come from our FE Industrial and Systems bank, written to the same specification as the exam. Try each one before opening the solution.

Problem 1

A manufacturing firm evaluates three strategic capacity expansion alternatives (Small Plant, Medium Plant, Large Plant) to meet uncertain 5-year demand for a new electric vehicle powertrain component. Market analysis identifies three discrete economic states of nature with estimated probabilities: - Low Demand: P(S1) = 0.20 - Medium Demand: P(S2) = 0.50 - High Demand: P(S3) = 0.30 Payoff matrix (net present values in USD): - Small Plant: S1 = USD 120,000; S2 = USD 180,000; S3 = USD 180,000 - Medium Plant: S1 = USD 80,000; S2 = USD 240,000; S3 = USD 260,000 - Large Plant: S1 = -USD 45,000 (Loss); S2 = USD 260,000; S3 = USD 350,000 Calculate the Expected Monetary Value (EMV) for the optimal decision alternative and determine the Expected Value of Perfect Information (EVPI).

  1. AExpected monetary value is USD 168,000 (Expected value of perfect information EVPI = USD 91,000)
  2. BExpected monetary value is USD 214,000 (Expected value of perfect information EVPI = USD 45,000)
  3. CExpected monetary value is USD 240,000 (Expected value of perfect information EVPI = USD 19,000)
  4. DExpected monetary value is USD 226,000 (Expected value of perfect information EVPI = USD 33,000)correct
Show the solution

**Step 1: Calculate Expected Monetary Value ($EMV$) for Each Decision Alternative** - **Small Plant:** $$EMV_{Small} = 0.20(120{,}000) + 0.50(180{,}000) + 0.30(180{,}000)$$ $$EMV_{Small} = 24{,}000 + 90{,}000 + 54{,}000 = \text{USD } 168{,}000$$ - **Medium Plant:** $$EMV_{Medium} = 0.20(80{,}000) + 0.50(240{,}000) + 0.30(260{,}000)$$ $$EMV_{Medium} = 16{,}000 + 120{,}000 + 78{,}000 = \text{USD } 214{,}000$$ - **Large Plant:** $$EMV_{Large} = 0.20(-45{,}000) + 0.50(260{,}000) + 0.30(350{,}000)$$ $$EMV_{Large} = -9{,}000 + 130{,}000 + 105{,}000 = \text{USD } 226{,}000$$ The optimal decision under expected value is **Large Plant** with $EMV^* = \text{USD } 226{,}000$. **Step 2: Calculate Expected Value with Perfect Information ($EVwPI$)** If perfect information could foresee the exact state of nature: - If Low Demand ($P = 0.20$): Choose Small Plant $\implies \text{Payoff } = \text{USD } 120{,}000$ - If Medium Demand ($P = 0.50$): Choose Large Plant $\implies \text{Payoff } = \text{USD } 260{,}000$ - If High Demand ($P = 0.30$): Choose Large Plant $\implies \text{Payoff } = \text{USD } 350{,}000$ $$EVwPI = 0.20(120{,}000) + 0.50(260{,}000) + 0.30(350{,}000)$$ $$EVwPI = 24{,}000 + 130{,}000 + 105{,}000 = \text{USD } 259{,}000$$ **Step 3: Calculate Expected Value of Perfect Information ($EVPI$)** $$EVPI = EVwPI - \max(EMV) = 259{,}000 - 226{,}000 = \text{USD } 33{,}000$$ The maximum expected monetary value is **USD 226,000** and the firm should pay no more than **USD 33,000** for perfect market research.

Problem 2

An engineering project manager performs Earned Value Management (EVM) for a capital plant upgrade at Month 6 of a 12-month schedule. The total authorized Budget at Completion is BAC = 1,000,000 USD. At the review date, the project control metrics are: • Planned Value (PV) = 450,000 USD • Earned Value (EV) = 380,000 USD • Actual Cost (AC) = 420,000 USD Calculate the Cost Performance Index (CPI) and the projected Estimate at Completion (EAC), assuming the project will continue to perform at its current cost efficiency rate.

  1. A1.105 CPI and Estimate at Completion EAC = 905,000 USD (Under budget and ahead of schedule)
  2. B0.844 CPI and Estimate at Completion EAC = 1,185,000 USD (Lagging schedule performance)
  3. C0.905 CPI and Estimate at Completion EAC = 1,105,000 USD (Over budget and behind schedule)correct
  4. D0.950 CPI and Estimate at Completion EAC = 1,050,000 USD (Within acceptable contingency margin)
Show the solution

**Step 1: Compute Cost and Schedule Variances** From the FE Reference Handbook (Engineering Management / Earned Value Analysis): - Cost Variance: $$\text{CV} = \text{EV} - \text{AC} = 380\text{ USD}{,}000 - 420\text{ USD}{,}000 = -40\text{ USD}{,}000 \quad (\text{over budget})$$ - Schedule Variance: $$\text{SV} = \text{EV} - \text{PV} = 380\text{ USD}{,}000 - 450\text{ USD}{,}000 = -70\text{ USD}{,}000 \quad (\text{behind schedule})$$ **Step 2: Calculate Performance Indices (CPI and SPI)** - Cost Performance Index: $$\text{CPI} = \frac{\text{EV}}{\text{AC}} = \frac{380\text{ USD}{,}000}{420\text{ USD}{,}000} = 0.90476 \approx 0.905$$ (For every dollar spent, only 0.905 USD of planned work is delivered). - Schedule Performance Index: $$\text{SPI} = \frac{\text{EV}}{\text{PV}} = \frac{380\text{ USD}{,}000}{450\text{ USD}{,}000} = 0.8444 \approx 0.844$$ **Step 3: Calculate Estimate at Completion (EAC)** Assuming future cost performance continues at the established cumulative $\text{CPI}$: $$\text{EAC} = \frac{\text{BAC}}{\text{CPI}} = \frac{1\text{ USD}{,}000{,}000}{0.90476} = 1\text{ USD}{,}105{,}263 \approx 1\text{ USD}{,}105{,}000$$ Conclusion: The metrics are **0.905 CPI and Estimate at Completion EAC = 1,105,000 USD** (Option C).

Problem 3

Continuous quality improvement and total quality management frameworks guide industrial engineering practice. Select the THREE statements that correctly characterize Deming PDCA (Plan-Do-Check-Act) and ISO 9001 quality management principles.

  1. AIn the "Plan" phase, the engineering team establishes baseline performance metrics, investigates root causes of process defects, and designs a targeted operational change.
  2. BIn the "Check" phase, pilot performance data are analyzed against baseline objectives to verify whether process improvements achieved predicted statistical significance.
  3. CISO 9001 incorporates a risk-based thinking framework that systematically identifies and mitigates risks across process interactions before execution.
  4. DIn the "Act" phase, all pilot modifications are completely undone regardless of results to preserve initial operating procedures.
Show the solution

**Step 1: Review PDCA Quality Management Framework** 1. **Plan:** Identify problem, map process, analyze root causes (Ishikawa, Pareto), and formulate a measurable intervention plan. Statement A is correct. 2. **Do:** Execute the plan on a controlled pilot or small-scale basis. 3. **Check (Study):** Measure pilot outcomes, analyze key performance metrics, and compare against goals. Statement B is correct. 4. **Act:** Standardize successful modifications into standard operating procedures (SOPs) or iterate if goals were unmet. 5. **ISO 9001:** Emphasizes customer satisfaction, process approach, and risk-based thinking. Statement C is correct. **Step 2: Distractor Analysis** - Statement D is false: Successful pilot improvements are standardized into official work instructions, not discarded. Correct choices: **A, B, and C**.

Find out where you actually stand

A free 20-question diagnostic across every FE Industrial and Systems knowledge area, scored in the real exam interface. You get a projected score and the areas costing you the most — so you know whether Engineering Management is where your time should go at all.

Start the free Industrial & Systems diagnostic

Retaking the FE Industrial and Systems exam?

Copy the scores from your NCEES diagnostic report and see whether Engineering Management is where your next attempt gains the most points, or whether another area deserves the time first.

Analyze my diagnostic report

Other FE Industrial and Systems knowledge areas