Problem 1
A project consists of four sequential activities on the critical path: A (4 days), B (6 days), C (5 days), D (3 days), for a normal total of 18 days. Activity B can be crashed by up to 2 days at a cost of $300 per day crashed. If the project is crashed by the maximum 2 days on activity B, what is the new project duration and the total crashing cost?
- A16 days; $600 extracorrect
- B16 days; $300 extra
- C18 days; $600 extra
- D14 days; $600 extra
Show the solution
With only one path through the four activities, that path is by definition the critical path, so any activity on it directly controls the project duration. The normal duration is the sum of all four activities: 4+6+5+3 = 18 days. Crashing activity B by its full available 2 days removes those 2 days directly from the critical path, since there is no other path to become newly critical and limit the benefit: new duration = 18 - 2 = 16 days. The crashing cost is simply the per-day crash cost times the number of days crashed: extra cost = 300/day * 2 days = 600. If there had been a second, nearly-as-long path, crashing B further than that path's slack would have stopped shortening the project, but that is not the case here.
Problem 2
An earthmoving contractor is assembling a fleet for a highway embankment project. Match each piece of equipment to the task it is best suited to perform.
Show the solution
Equipment selection on an earthwork job is an economic decision driven by haul distance and by what each machine can do in one pass. THE SCRAPER occupies a specific niche: it loads itself, carries the material and spreads it on arrival, which makes it efficient over medium hauls where a separate excavator-and-truck fleet would cost more, though it loses out to trucks on long hauls and to a dozer on very short ones. THE BACKHOE digs below its own grade, which is what distinguishes it from a front shovel and makes it the standard machine for trenches, footings and utility work. THE VIBRATORY ROLLER compacts by adding dynamic energy to static weight, which is far more effective in granular soils where vibration rearranges particles into a denser packing — in cohesive soils a sheepsfoot roller's kneading action works better instead, a distinction that matters when the fill changes. THE MOTOR GRADER is a finishing machine, its long wheelbase and adjustable blade producing the flat, accurately sloped surface that the pavement structure will be built on. The two unused labels describe a pile driver and a transit mixer, both common on sites but neither an earthmoving machine.
Problem 3
A highway construction grading project involves an earthwork cut and fill operation. The required roadway embankment fill requires $13{,}200\text{ m}^3$ of compacted material. The excavated cut soil in its natural in-situ state has a shrinkage factor of $12\%$ ($Shrinkage = 0.12$, meaning $1.0\text{ m}^3$ of bank volume compacts to $0.88\text{ m}^3$ of fill) and a swell factor of $20\%$ upon excavation into haul trucks ($Swell = 0.20$). Haul trucks used on the site have a struck loose capacity of $15.0\text{ m}^3$ per trip. The total number of loose truckloads required to haul the excavated bank soil needed to construct the embankment is most nearly:
- A880
- B960
- C1,050
- D1,200correct
Show the solution
Step 1: Identify given volume transformation relationships in construction earthwork: - Required compacted volume: $V_{\text{compacted}} = 13{,}200\text{ m}^3$ - Shrinkage factor: $S_h = 12\% = 0.12$ - Swell factor: $S_w = 20\% = 0.20$ - Truck loose capacity: $C_{\text{truck}} = 15.0\text{ m}^3$/load Step 2: Reference the NCEES FE Reference Handbook (Construction, Earthwork Volume Transformations): - The relationship between compacted volume and in-situ bank volume: $$V_{\text{compacted}} = V_{\text{bank}} \times (1 - S_h)$$ $$V_{\text{bank}} = \dfrac{V_{\text{compacted}}}{1 - S_h} = \dfrac{13{,}200\text{ m}^3}{1 - 0.12} = \dfrac{13{,}200\text{ m}^3}{0.88} = 15{,}000\text{ m}^3$$ Step 3: Convert the bank volume to loose volume for transport: - When in-situ soil is excavated into haul units, it swells due to particle loosening: $$V_{\text{loose}} = V_{\text{bank}} \times (1 + S_w)$$ $$V_{\text{loose}} = 15{,}000\text{ m}^3 \times (1 + 0.20) = 15{,}000 \times 1.20 = 18{,}000\text{ m}^3$$ Step 4: Calculate the required number of truckloads: $$\text{Number of truckloads} = \dfrac{V_{\text{loose}}}{C_{\text{truck}}} = \dfrac{18{,}000\text{ m}^3}{15.0\text{ m}^3/\text{load}} = 1{,}200\text{ loads}$$ Distractor Analysis: - Option A (880 loads) erroneously divides the compacted volume directly by the truck capacity ($13{,}200 / 15 = 880$), completely ignoring soil swell and shrinkage. - Option B (960 loads) applies swell to compacted volume rather than bank volume. - Option C (1,050 loads) correctly calculates bank volume (15,000 m³) but omits swell when loading trucks ($15{,}000 / 15 = 1{,}000$). - Option D (1,200 loads) correctly applies both the shrinkage factor to find bank volume and the swell factor to find transport volume.