Transportation Engineering accounts for 9 of the 110 questions — 8.2% of your exam. It is one of the three heaviest areas on this paper, so it is worth your study time before almost anything else.

Questions9
Share of exam8.2%
Rank by weight3/18
In our bank36

What Transportation Engineering covers

On the FE Civil exam this area covers geometric design of horizontal and vertical curves, sight distance, traffic flow and capacity, signal timing, highway safety, and pavement design.

What the questions look like: A curve radius or length, a stopping sight distance, a signal capacity, or a traffic flow relationship.

Worth knowing cold: Sight distance and curve geometry account for most of the computation here, and both come straight from the Handbook once you identify the case.

3 free Transportation Engineering practice problems

These come from our FE Civil bank, written to the same specification as the exam. Try each one before opening the solution.

Problem 1

A horizontal curve is being designed for a 100 km/h roadway. Using a perception-reaction time of 2.5 s and a deceleration rate of 3.4 m/s² on level ground, the required stopping sight distance is calculated. If the available sight distance around the curve, limited by roadside obstructions, is only 170 m, is the available sight distance adequate?

  1. AYes — required SSD (150.2 m) is less than the available 170 m
  2. BNo — required SSD (182.9 m) exceeds the available 170 mcorrect
  3. CYes — required SSD (113.5 m) is less than the available 170 m
  4. DThe comparison cannot be made without knowing the curve radius
Show the solution

Compute the required stopping sight distance and compare it against what is physically available. v = 100 km/h = 27.78 m/s. Reaction distance: d r = vt = 27.78(2.5) = 69.44 m. Braking distance: d b = v²/(2a) = 27.78²/(2 × 3.4) = 771.7/6.8 = 113.5 m. SSD = 69.44 + 113.5 = 182.9 m. Since 182.9 m > 170 m available, the sight distance is NOT adequate — obstructions (a cut slope, retaining wall, or vegetation) would need to be addressed, or the design speed reduced. (D) is a distractor: the available sight distance is given directly as a site constraint in this problem; the curve radius would be relevant for calculating required horizontal clearance from the obstruction to meet a given SSD, but it isn't needed to compare the two sight-distance values given here.

Problem 2

A horizontal curve has a radius of 250 m, and the required stopping sight distance is 180 m (less than the curve length, so the sight line is a chord across the inside of the curve). Using the middle ordinate formula, M = R*(1 - cos(delta/2)), where delta = S/R is the angle (in radians) subtended by the sight distance arc, what horizontal clearance (middle ordinate) must be provided from the roadway centerline to any sight obstruction, in meters? Round to 2 decimal places.

Show the solution

On a horizontal curve, the sight line between a driver and a point ahead is a straight chord, while the roadway itself curves away from that chord — the middle ordinate M measures the maximum gap between the curved roadway centerline and that straight sight line, which is exactly the clearance that must be kept free of sight obstructions (like a cut slope, wall, or dense vegetation) along the inside of the curve. First find the subtended angle: delta = S/R = 180/250 = 0.72 radians. Then the middle ordinate: M = R*(1-cos(delta/2)) = 250*(1-cos(0.36)) = 250*(1-0.9359) = 250(0.0641) = 16.03 m, which rounds to 16.03 m. This calculation is the geometric basis for horizontal sight-distance clearance requirements on curves, and explains why a sharper curve (smaller R) for the same sight distance S can actually require MORE middle-ordinate clearance in some ranges, since the relationship between R and M is not simply proportional.

Problem 3

A two-lane rural undivided highway has lanes of width W = 3.60 m. The horizontal curve is designed with a full superelevation rate of e = 0.060 m/m (6.0%) developed by rotating the pavement cross-section about the central roadway centerline (CL). According to AASHTO highway design standards, the maximum allowable relative gradient between the edge of the traveled way and the centerline axis of rotation is Delta = 0.50% (0.0050 m/m, corresponding to 1:200). Refer to the accompanying technical diagram [FE-CIV-1732]. What is the minimum required superelevation runoff length Lr (in meters) to transition the pavement cross-section from the reverse crown (+2% outer edge) to full superelevation (+6% outer edge)?

  1. A36.0 m
  2. B43.2 mcorrect
  3. C54.0 m
  4. D72.0 m
Show the solution

Step 1 - Identify the Geometric Superelevation Parameters: - Rotated lane width from centerline: $W = 3.60\text{ m}$ - Design superelevation rate: $e = 0.060\text{ m/m} = 6.0\%$ - Maximum relative edge slope: $\Delta = 0.50\% = 0.0050\text{ m/m}$ Step 2 - AASHTO Superelevation Runoff Formulation: The runoff length $L_r$ is the distance required to transition the outer edge of the traveled way from a reverse crown slope equal to the normal crown ($+2.0\%$) to full superelevation ($+6.0\%$), or proportionally: $$L_r = \frac{w \cdot n_1 \cdot e \cdot b_w}{\Delta}$$ where for rotation about the centerline with one lane on either side: - $w = 3.60\text{ m}$ (lane width) - $n_1 = 1$ (number of lanes rotated) - $e = 0.060$ (design superelevation rate) - $b_w = 1.00$ (adjustment factor for number of lanes rotated, $1.0$ for $1$ lane) - $\Delta = 0.0050$ (maximum relative profile slope) Step 3 - Numerical Computation: $$L_r = \frac{W \cdot e}{\Delta} = \frac{(3.60\text{ m})(0.060)}{0.0050} = \frac{0.2160\text{ m}}{0.0050} = 43.20\text{ m} \approx 43.2\text{ m}$$ Step 4 - Distractor Analysis: - Option A ($36.0\text{ m}$) results from using $e = 0.050$ instead of $0.060$ ($3.60 \times 0.050 / 0.005 = 36.0\text{ m}$). - Option C ($54.0\text{ m}$) results from using lane width $W = 4.50\text{ m}$. - Option D ($72.0\text{ m}$) results from rotating the entire two-lane roadway width ($7.20\text{ m}$) about the outer shoulder edge instead of rotating about the centerline. Therefore, the minimum required superelevation runoff length is 43.2 m (Option B).

Find out where you actually stand

A free 20-question diagnostic across every FE Civil knowledge area, scored in the real exam interface. You get a projected score and the areas costing you the most — so you know whether Transportation Engineering is where your time should go at all.

Start the free Civil diagnostic

Retaking the FE Civil exam?

Copy the scores from your NCEES diagnostic report and see whether Transportation Engineering is where your next attempt gains the most points, or whether another area deserves the time first.

Analyze my diagnostic report

Other FE Civil knowledge areas