Engineering Economics on the FE Other Disciplines exam

Engineering Economics accounts for 7 of the 110 questions — 6.4% of your exam. It sits in the middle of the paper by weight: too big to skip, not big enough to dominate your plan.

Questions7
Share of exam6.4%
Rank by weight9/14
In our bank24

What Engineering Economics covers

On the FE Other Disciplines exam this area covers time value of money, present and future worth, annual equivalent cost, rate of return, benefit-cost analysis, depreciation, and economic life and replacement analysis.

What the questions look like: A cash-flow problem solved with one factor from the Handbook interest tables, or a straight-line depreciation or benefit-cost ratio.

Worth knowing cold: Draw the cash-flow diagram before touching the calculator. Almost every mistake in this area is a sign or a timing error, not a factor lookup.

3 free Engineering Economics practice problems

These come from our FE Other Disciplines bank, written to the same specification as the exam. Try each one before opening the solution.

Problem 1

An industrial energy efficiency upgrade requires an initial capital expenditure of $P = \$180{,}000$ and provides uniform net annual energy cost savings of $A = \$45{,}000/\text{year}$ at the end of each year for $n = 6\text{ years}$, with negligible terminal salvage value. The corporate Minimum Attractive Rate of Return (MARR) is $10.0\%$. Using linear interpolation between standard interest rates: What is the internal rate of return (IRR) of the upgrade, and is the investment economically justified?

  1. A10.0% (equal to MARR baseline)
  2. B8.5% (below MARR error)
  3. C15.5% (overestimated return)
  4. D13.0% (with PW(12%) = +$5,013 and PW(14%) = -$5,008, economically justified since IRR > MARR)correct
Show the solution

**Step 1: Formulate Present Worth Equation for IRR** From the FE Reference Handbook (Engineering Economics / Rate of Return / Internal Rate of Return): The Internal Rate of Return $i^*$ is the discount rate that drives net present worth to zero: $$PW(i^*) = -P + A (P/A, i^*, n) = 0$$ $$-180{,}000 + 45{,}000 (P/A, i^*, 6) = 0 \implies (P/A, i^*, 6) = \frac{180{,}000}{45{,}000} = 4.000$$ **Step 2: Bracket IRR with Trial Interest Rates** Recall $(P/A, i, n) = \frac{(1+i)^n - 1}{i(1+i)^n}$: - At $i_1 = 12.0\%$: $$(P/A, 12\%, 6) = \frac{(1.12)^6 - 1}{0.12(1.12)^6} = \frac{1.973823 - 1}{0.12(1.973823)} = 4.111407$$ $$PW(12\%) = -180{,}000 + 45{,}000(4.111407) = -180{,}000 + 185{,}013 = +\$5{,}013$$ - At $i_2 = 14.0\%$: $$(P/A, 14\%, 6) = \frac{(1.14)^6 - 1}{0.14(1.14)^6} = \frac{2.194973 - 1}{0.14(2.194973)} = 3.888668$$ $$PW(14\%) = -180{,}000 + 45{,}000(3.888668) = -180{,}000 + 174{,}990 = -\$5{,}010$$ **Step 3: Interpolate for Exact IRR** $$i^* \approx 12.0\% + (14.0\% - 12.0\%) \times \frac{5{,}013 - 0}{5{,}013 - (-5{,}010)} = 12.0\% + 2.0\% \left(\frac{5{,}013}{10{,}023}\right) = 12.0\% + 2.0\%(0.50015) = 13.00\%$$ Since $\text{IRR} = 13.0\% > \text{MARR} = 10.0\%$, the project is economically attractive. Conclusion: The internal rate of return is **$13.0\%$**, which is economically justified.

Problem 2

A municipal public works department evaluates three mutually exclusive storm drainage pumping station designs for a regional watershed protection project. All designs have a useful service life of 20 years with zero salvage value ($S = 0$). The MARR is $i = 6.0\%$ per year ($(\text{A/P}, 6\%, 20) = 0.087184$). Economic data for the alternatives: - Alternative 1: Initial Cost $P_1 = \$1{,}200{,}000$, Annual O&M $C_1 = \$30{,}000$, Annual Flood Damage Reduction Benefit $B_1 = \$180{,}000$ - Alternative 2: Initial Cost $P_2 = \$1{,}800{,}000$, Annual O&M $C_2 = \$45{,}000$, Annual Flood Damage Reduction Benefit $B_2 = \$265{,}000$ - Alternative 3: Initial Cost $P_3 = \$2{,}500{,}000$, Annual O&M $C_3 = \$65{,}000$, Annual Flood Damage Reduction Benefit $B_3 = \$320{,}000$ Using incremental Benefit-Cost ratio analysis ($\Delta B / \Delta C$), which alternative is the economically preferred design?

  1. A1.34 (incremental ratio B/C of Alternative 1 vs Do-Nothing)
  2. B1.15 (incremental ratio B/C of Alternative 3 vs Do-Nothing)
  3. C0.85 (Do-Nothing selection threshold)
  4. D1.26 (incremental ratio ΔB/ΔC for Alternative 2 vs Alternative 1; preferred selection)correct
Show the solution

Step 1: Compute annual equivalent capital recovery and total annual cost for each design: $$(\text{A/P}, 6\%, 20) = \frac{0.06(1 + 0.06)^{20}}{(1 + 0.06)^{20} - 1} = 0.087184$$ - Alternative 1: $$\text{EUAC}_1 = \$1{,}200{,}000(0.087184) + \$30{,}000 = \$104{,}621 + \$30{,}000 = \$134{,}621$$ $$B_1 / C_1 = \frac{\$180{,}000}{\$134{,}621} = 1.337 > 1.0 \implies \text{Alternative 1 is economically viable (Defender)}$$ Step 2: Incremental analysis of Alternative 2 vs Alternative 1: $$\Delta P = \$1{,}800{,}000 - \$1{,}200{,}000 = \$600{,}000$$ $$\Delta C = \$600{,}000(0.087184) + (\$45{,}000 - \$30{,}000) = \$52{,}310 + \$15{,}000 = \$67{,}310$$ $$\Delta B = \$265{,}000 - \$180{,}000 = \$85{,}000$$ $$\frac{\Delta B}{\Delta C} = \frac{\$85{,}000}{\$67{,}310} = 1.263 > 1.0$$ Since $\Delta B / \Delta C > 1.0$, the additional investment in Alternative 2 is justified. Alternative 2 becomes the new Defender. Step 3: Incremental analysis of Alternative 3 vs Alternative 2: $$\Delta P = \$2{,}500{,}000 - \$1{,}800{,}000 = \$700{,}000$$ $$\Delta C = \$700{,}000(0.087184) + (\$65{,}000 - \$45{,}000) = \$61{,}029 + \$20{,}000 = \$81{,}029$$ $$\Delta B = \$320{,}000 - \$265{,}000 = \$55{,}000$$ $$\frac{\Delta B}{\Delta C} = \frac{\$55{,}000}{\$81{,}029} = 0.6787 < 1.0$$ Since $\Delta B / \Delta C < 1.0$, Alternative 3 fails the incremental benefit test and is rejected. Therefore, Alternative 2 is the preferred selection (option D).

Problem 3

A regional municipal public works authority is evaluating a public flood mitigation diversion canal project with a useful life of N = 20 years and an effective annual discount rate of i = 6.0%: - Initial capital construction cost: P = $8,000,000 - Annual routine inspection and levee maintenance: C_ann = $120,000 per year - Annual direct public flood damage reduction benefits: B_ann = $950,000 per year - Estimated terminal salvage value of land and right-of-way at year 20: S = $1,500,000 What is the conventional Benefit-Cost ratio (B/C) of this public infrastructure project?

  1. A1.05
  2. B1.42
  3. C1.11
  4. D1.22correct
Show the solution

Step 1 - Compound Interest Factors for $i = 6.0\%$, $N = 20\text{ years}$: $$(1 + i)^N = (1.06)^{20} = 3.207135$$ - Capital Recovery factor $(A/P, 6\%, 20)$: $$(A/P, 6\%, 20) = \frac{i(1 + i)^N}{(1 + i)^N - 1} = \frac{0.06(3.207135)}{2.207135} = \frac{0.192428}{2.207135} = 0.087184$$ - Sinking Fund factor $(A/F, 6\%, 20)$: $$(A/F, 6\%, 20) = \frac{i}{(1 + i)^N - 1} = \frac{0.06}{2.207135} = 0.027184$$ Step 2 - Equivalent Uniform Annual Cost of Capital Recovery ($CR$): $$CR = P (A/P, 6\%, 20) - S (A/F, 6\%, 20)$$ $$P (A/P) = \$8,000,000 \times 0.087184 = \$697,472/\text{year}$$ $$S (A/F) = \$1,500,000 \times 0.027184 = \$40,776/\text{year}$$ $$CR = \$697,472 - \$40,776 = \$656,696/\text{year}$$ Step 3 - Total Equivalent Uniform Annual Cost ($C_{\text{total}}$): $$C_{\text{total}} = CR + C_{\text{ann}} = \$656,696 + \$120,000 = \$776,696/\text{year}$$ Step 4 - Calculate Conventional Benefit-Cost Ratio: $$B/C = \frac{B_{\text{ann}}}{C_{\text{total}}} = \frac{\$950,000/\text{year}}{\$776,696/\text{year}} = 1.2231 \approx 1.22$$ Because $B/C > 1.0$, the public infrastructure project is economically justified. The B/C ratio is 1.22 (Option D).

Find out where you actually stand

A free 20-question diagnostic across every FE Other Disciplines knowledge area, scored in the real exam interface. You get a projected score and the areas costing you the most — so you know whether Engineering Economics is where your time should go at all.

Start the free Other Disciplines diagnostic

Retaking the FE Other Disciplines exam?

Copy the scores from your NCEES diagnostic report and see whether Engineering Economics is where your next attempt gains the most points, or whether another area deserves the time first.

Analyze my diagnostic report

Other FE Other Disciplines knowledge areas

Engineering Economics on other FE exams

The same knowledge area is weighted differently on each exam, and the questions differ with it.